October, beginning to look like a home

October

The house comes together...


October achievements:
  • Kitchen and bathrooms cabinetry installed
  • Stairs installed
  • Painting, internal and external 90% done
  • Tiling to walls and floors wet areas
  • Hot water tank installed
  • Ceiling to alfresco installed
  • Lighting installed (not without a little drama!)
  • Fans, electrical, spa and dishwasher installed


Bedroom 5


Downstairs hall

Feature tile to ensuite shower

Ensuite walk in shower

Front of house

                    Kitchen
                                Walk in pantry   


Lounge room doors, stained

Bottom of staircase

Spring Has Sprung: September


Spring has sprung
September progress

Well, Septmber came and went in a hurry and while plenty of photos were taken they didn't make it to a post, until now that is...


Front of house






SOME internal pictures  (I have heaps!!)
Bedroom 5

                           Dining room window


Lounge and dining room doors


 
                                          Lounge window                                                View from Master suite
                                                                                       





Friday, 9 November 2012

August: Part 2

August, house frame completion

We have been incredibly busy building our new home, and we also learned of a new addittion to our little family due next year, so suffice to say blogging has fell by the wayside.

But, here are some photos to show our ENORMOUS progress!!

August highlights:

  • Frame commenced and completed
  • 2nd storey frame and subfloor completed
  • Ducted aircon "rough-in" complete
  • Power and water to house
  • Colourbond roof commenced
  • Temporary downpipes woking, but no rain
  • Scaffolding and a ladder in the stair void





















Thursday, 16 August 2012

We have lift off!


August

The sun is shining and the progress is phenomenal!  If a picture says 1000 words, I have written a blog for the millions...

IN 14 DAYS WE WENT FROM A SCRAPED BLOCK TO A (NEARLY) COMPLETE HOUSE FRAME


2nd August, 2012 - Framework for slab set and fruit boxes (aka waffle pod) galore! 




4th August, 2012 - Wafflepod set


4th August, 2012 - Wafflepod set




4th August, 2012 - Wafflepod set




6th August - Brand new shiny slab!

6th August - View from rear 




8th August, 2012 Our new water tank was delivered.  Waiting for the slab to cure.


The aftermath of the timber delivery, they broke every branch on our only tree.  A little bit sad about it.
 
9th August 2012 The timber has arrived!






10 August, 2012 The bottom half of the house is up.  And we have a fence.


11th August, 2012 The bottom storey frame is completed



14th August 2012, Most of the top floor frame is up.  We also have a port-a-loo squeezed on the front of the block.

15th August, 2012 view from the rear of the block



15th August, 2012 Thinking the loo makes the house look fairly small :/


15th August, 2012 Our littlest Site Supervisor throwing driveway rubble on to the road.